Houghton Solid Waste Transfer Station

industrial, structural-steel
Arrow
Arrow
This replacement design required the facility to be operational at 80% capacity during construction. ABKJ devised a means of raising and retrofitting the existing roof structural framing one half at a time to allow the station open for the entire construction duration. Awards: 2011 Project of the Year (under $5 million) - American Public Works Association Washington Chapter
ArrowArrow
Slider